Iraqi Court of Cassation Confirms the Consequences of Late Performance Guarantees in Government Contracts

The Iraqi Federal Court of Cassation has confirmed that a successful bidder may lose its right to complete a government contracting process if it fails to provide the required security within the prescribed period. Submitting a performance guarantee after the bidder has been declared in default does not automatically restore its contractual position.

Background

The dispute arose from the award of a contract for the transportation of petroleum products to a private company. Following the award, the company was required to provide the prescribed security and complete the remaining contracting procedures within the applicable period.

The contracting authority treated the company as a defaulting bidder because it had not provided the performance guarantee on time and subsequently proceeded with the next-ranked bidder. The company commenced proceedings seeking to complete the contract and prevent the authority from contracting with competitors.

Court’s Findings

The Court found that the performance guarantee had been issued only after the relevant period had expired and after the authority had formally treated the company as being in default.

The subsequent issuance of the guarantee did not invalidate the measures taken under the applicable government contracting rules. Because the authority had proceeded to the next-ranked bidder in accordance with the prescribed process, the original bidder had no legal basis for requiring completion of the contract.

Practical Implications

Companies participating in Iraqi government tenders should identify the deadline for providing the performance guarantee, coordinate with the issuing bank in advance and verify that the guarantee complies with the tender documents.

They should not assume that an award decision alone creates a final contract. Any permitted extension should be obtained in writing before the deadline, and evidence of the issuance and delivery of the guarantee should be retained.

Conclusion

The decision demonstrates that compliance with public procurement deadlines is a substantive requirement. A delay in providing the required guarantee may result in the bidder being treated as having defaulted and the award being transferred to another company.