Skip to main content

Etihad Law

Delivery Delays in Iraqi Supply Contracts

Delivery delays are the failure of a supplier to deliver the contract goods at the time prescribed by the contract or, in the absence of a contractual time, within a reasonable period. Under Iraqi law, the consequences of delay are determined by reference to the contractual provisions on time of performance, the general provisions of the Iraqi Civil Code No. 40 of 1951 on the consequences of delay, and the specific provisions on the contract of sale where the contract is so characterised. The framework engages the doctrinal requirement of formal notice (إعذار), the remedies available to the purchaser, and the interaction with force majeure where the delay is attributable to circumstances beyond the supplier’s control.

Time of Performance

The time of performance is established by the contract. The contractual time may be defined as a specific date or period, as a period from the conclusion of the contract or from another defined event, or by reference to a delivery schedule incorporated into the contract. Where the contract does not specify the time, the Civil Code provides that performance is due within a reasonable period determined by reference to the nature of the obligation and the surrounding circumstances. The contract may distinguish between binding delivery dates and indicative delivery dates, with corresponding implications for the consequences of delay; the drafting should be sufficiently precise to support the characterisation.

Formal Notice Requirement

The Iraqi Civil Code, the obligor is, in general, not deemed to be in delay until a formal notice is served on him by the obligee, requiring the performance of the obligation. The formal notice is a substantive procedural requirement of Iraqi law, the satisfaction of which is, in general, a precondition to the entitlement to claim damages for delay. The Civil Code identifies circumstances in which the formal notice is not required, including:

  • Where the parties have agreed that the obligor shall be in delay on the mere expiry of the time fixed for performance
  • Where performance has become impossible by reason of the obligor’s act or where the time of performance has lapsed without performance and cannot be made up
  • Where the formal notice has been waived by the obligor or rendered pointless by the obligor’s conduct
  • Where the obligation arises from an unlawful act

The formal notice should, in general, be served in writing with sufficient particularity as to the obligation invoked, the performance required, and the period within which performance is to be rendered.

Damages for Delay

Where the supplier is in delay, the purchaser is entitled to compensation for the loss caused by the delay under the Civil Code. The compensation engages the actual loss sustained by the purchaser, including direct losses and consequential losses to the extent foreseeable at the conclusion of the contract under Civil Code. The quantification of damages requires the demonstration of the loss with reasonable certainty, supported by the evidentiary record. Where the contract includes a liquidated damages clause, the agreed amount operates as the pre-fixed compensation for the relevant categories of breach.

Liquidated Damages for Delay

Liquidated damages clauses for delay conventionally calibrate the damages by reference to a daily or weekly rate applied to the value of the delayed goods, subject to a cumulative cap. The Civil Code, the court retains a power to adjust the agreed amount where it is shown to be manifestly disproportionate to the actual loss or where the principal obligation has been performed in part. The drafting of liquidated damages clauses should accordingly be calibrated to a reasonable estimate of the loss likely to be sustained, with documentation supporting that calibration. The clause should specify:

  • trigger of the liquidated damages, including the time from which they accrue
  • rate of accrual
  • cumulative cap, where one applies
  • interaction with other remedies, including whether the liquidated damages constitute the exclusive remedy for delay or operate in addition to damages and termination
  • procedure for the deduction of liquidated damages from amounts payable to the supplier

Specific Performance

Under Civil Code, the purchaser is, in general, entitled to require the supplier to perform the obligation specifically where this is possible. Specific performance of delivery obligations engages the requirement that the supplier deliver the contract goods notwithstanding the delay. Specific performance is the primary remedy of Iraqi law for the breach of obligations to deliver, in distinction to common law systems where damages are the primary remedy. Where specific performance has become impossible, or where the purchaser elects to pursue alternative remedies, damages or rescission are available.

Termination for Prolonged Delay

Where the delay is material and prolonged, the purchaser may, under the Civil Code, seek the rescission of the contract together with compensation for loss sustained. The materiality of the delay is assessed by reference to the nature of the contract, the importance of the time of performance to the purchaser’s broader operations, and the prospect of subsequent performance. The contract may specify the period of delay after which the purchaser is entitled to terminate, including by reference to a defined number of days or to the persistence of the delay following formal notice. The termination should be effected in accordance with the contractual procedures and, where required, with judicial recourse.

Interaction with Force Majeure

Delay attributable to force majeure within the meaning of Civil Code engages the suspension of the supplier’s obligation for the duration of the force majeure, rather than constituting actionable delay. The interaction between the delay framework and the force majeure framework engages substantive questions of construction, particularly where the force majeure is partial, where it affects some but not all categories of supply, or where its impact on the supplier’s capacity to perform is contested. The purchaser is, in general, entitled to require evidence supporting the supplier’s invocation of force majeure before treating delivery delays as excused under that doctrine.

Practical Considerations

The management of delivery delays in Iraqi supply chain practice engages substantive operational and legal considerations. Common causes of delay particular to Iraqi operations include customs clearance delays at points of entry, transport disruptions on the principal road and maritime routes, banking and payment infrastructure delays affecting the release of letters of credit, regulatory authorisation delays affecting sectoral imports, and supplier-side operational issues. The management of delays engages the early identification of emerging delays, the substantive engagement with the supplier on the causes, the assessment of the contractual and operational implications, the issuance of formal notice where appropriate, and the deployment of contractual remedies in a structured manner.

Causation and Mitigation

The purchaser’s recovery for delay is subject to the requirements of causation and mitigation. The purchaser must establish that the loss claimed is the consequence of the delay and not of independent causes. The purchaser is, additionally, bound to mitigate the loss by taking reasonable steps to limit its impact, including the procurement of substitute supply where commercially feasible. The failure to mitigate may reduce or defeat the recovery.

How We Can Help

Etihad Law Firm advises on delivery delays in Iraqi supply contracts, including the assessment of contractual time provisions, the issuance and response to formal notices under the Civil Code, the calculation of damages for delay, the drafting and enforcement of liquidated damages clauses, the conduct of termination for prolonged delay, the assessment of force majeure invocations, and the conduct of disputes arising from delivery delays.